Industrial Equipment Replacement
Air House & Regenerative Thermo Oxidizer (RTO) Replacement Project
Background
- Customer/Location: Paint facility located in West Michigan
- This paint facility is primarily an automotive-based tier 1 supplier and was facing a dilemma. The dilemma was knowing that replacement of their aging HVAC & RTO system was badly needed, but downtime available was very limited due to an extremely high production demand.
- Throughout the budgeting and design process, production continued to ramp up, which meant the allowable downtime continued to shrink.
- The original downtime shrank from 3 months, to 2 months, to 2 weeks, and finally to just 9 days.
- Due to the above time constraints, a total re-design was incorporated to perform the following:
- Install a single structure/stand next to the plant
- Install a mechanical room at the base of the new structure
- Demolition of existing regenerative thermal oxidizer (RTO)
- Install a new RTO
- Installation of (6) new Air Houses
- Demolition of existing Air Houses
- MEP installation inside mechanical room
- Energy Management Controls
- Replacement of roof-mounted exhaust fans and stacks
- Duct across the roof
- Plumbing of mechanical room and mechanical room equipment
- Nine day change over to new system including the demolition of existing
Objective
Upgrade the system to meet the new design parameters of 70°F at 70% Relative Humidity for all units and zones, including as basis for Humidification for 100% Outdoor Air units.
Equipment
- Recirculating Air House:
- Booth #1 › 60,000 CFM Design basis
- Booth #2 › 60,000 CFM Design basis
- Booth #3 › 40,000 CFM Design basis
- 100% Outdoor Air House
- Booth #1 › 30,000 CFM Design basis
- Booth #2 › 30,000 CFM Design basis
- Booth #3 › 40,000 CFM Design basis
- 340 Ton Heat Reclaim Chiller
- 390 Ton VFD Screw Chiller
- 150 H.P. Humidification Boiler
- RTO
- RTO Heat Reclaim Coil
- 13 Pumps with VFD's
- Energy Management Controls
- Cooling Tower
Results
- Completed the project in 8 days!
- Product First Time Thru (FTT) rate improved on day one
- Elimination of Boiler System previously required for heating
- Increased quality of product
- Greatly improved system control
- And much more!